Council chooses a major refurbishment of the Recreation Centre (Option 2)
- DecidedOption 2: refurbish and upgrade the Recreation Centre as the Wanneroo Community Hub
- CostAbout $14.2 million
- DeadlineFinished by March 2029, within the State's $5 million funding agreement
- NextThe City will ask users and residents for their views, then report back to Council
Read moreShow less
What happened?
At the 24 November 2026 Council meeting, Council endorsed Option 2 as the preferred way to turn the Recreation Centre into the Wanneroo Community Hub. Councillors had been shown four options:
- Option 1: repairs and compliance work only, about $8.2 million
- Option 2: refurbish and upgrade, about $14.2 million (chosen)
- Option 3: new single-storey building, about $24.3 million
- Option 4: new two-storey building, about $27.3 million
Council asked the City to consult the community and stakeholders, and to report back before moving to detailed design.
What did my amendment add?
I moved an amendment, seconded by Cr Huntley, directing the City to review the project schedule so the Community Hub is finished by March 2029.
The City's timeline had building running until May 2029, two months after the State Government's $5 million funding agreement ends on 29 March 2029, which put that money at risk. The Member for Wanneroo, Sabine Winton MLA, has confirmed her support for Option 2 depends on it being delivered by March 2029.
Hiring the architect while the community is being consulted lets design start in April 2027 instead of June 2027, with building from March 2028 to February 2029.
What does it mean for you?
You would get new community rooms, a craft room with a kiln, a bigger kitchen, more toilets and showers, a Changing Place accessible toilet, and a building that can be used as an evacuation centre.
The indoor basketball court would go, and there is no room for a Scout hall or café, so some groups would need to move. Parts of the centre may need to close during building.
What happens next?
The City will review the schedule to meet the March 2029 deadline. It may consult users and residents over December 2026 and January 2027, then report the results back to Council before detailed design.